WORD LISTS

Peter Close GDFO

Thu Feb 24 09:56:52 EST 2011
By Ian B. (Solihull United Kingdom)
prioritise
Gas Distribution is committed to customer service excellence, prioritising it alongside safety and financial performance.
optimise
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m.
c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
optimisation
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m.
c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
decommission
Remaining investments are primarily driven by regulatory requirements or IS asset health upgrades.
d) £26m of Opex costs are required for archiving and decommissioning, incremental IS running costs that cannot be capitalised and activities required to implement business change.
programme
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
functionality
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
organisational
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes.
b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value under ...
rationalisation
These include:
a) Contact Centre Strategy – Contact Centre rationalisation project, value circa £2m/year operating efficiencies and circa £6M/year property rationalisation.
b) Customer Services Incentive – estimated +/- £12m.

8.
summarise
The options are summarised in the table below:
5.6
capitalise
Remaining investments are primarily driven by regulatory requirements or IS asset health upgrades.
d) £26m of Opex costs are required for archiving and decommissioning, incremental IS running costs that cannot be capitalised and activities required to implement business change.
grid
National Grid plc
Executive Committee
UK Gas Distribution Front Office Update
A paper by Mark Fairbairn, Executive Director, Gas Distribution
1.
trend analysis
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analysis
incremental
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
severance
To deliver the full scope and benefits will require an additional investment of £21m Capex and £3.6m of severance.
workload
The deployment window is limited to a 7-month period from April and October to avoid peak Emergency and Repair workload during the winter.
handoff
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
standardise
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
integrate
The GDFO deployment will be integrated with the changes associated with the introduction of the new operating model to ensure a clear and consistent message is articulated.
8.3
maximise
The programme also seeks to deliver more effective controls, these are essential to ensure that business process performance is maximised, risks to business objectives are minimised and compliance obligations are met.
workflow
Other improvements include:
a) automation and reduction of labour intensive and inconsistently operated manual processes;
b) a step change in the ease of field data capture through improved scripting and workflow on mobile devices;
c) Improved data quality through system driven data cleanse prior to load into new systems suite.
scheduling
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m.
c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
minimise
The programme has worked to reduce the impact of these increases and minimise the risk of future cost increases.
price control
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
update
National Grid plc
Executive Committee
UK Gas Distribution Front Office Update
A paper by Mark Fairbairn, Executive Director, Gas Distribution
1.
distribution
National Grid plc
Executive Committee
UK Gas Distribution Front Office Update
A paper by Mark Fairbairn, Executive Director, Gas Distribution
1.
information system
Therefore the following functionality would not be delivered:
 Mobile geographical information system for the field force, this will result in the continued use of CD maps.
stabilisation
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
customer
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
deliver
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
automate
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
scope
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
implementation
Release 2 and 3 will have a phased deployment that mitigates the risk associated to big bang implementation events.
handover
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
automation
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
workforce
It will support work planning, scenario analysis and project management.
b) A Customer Relationship Management system (SAP CRM) coupled with leading Contact Centre technologies (Telephony, IVR, Voice recording, Workforce management).
utilisation
This will require manual paper based processes to address the lost of automation these solutions will deliver.
b) Cost impact – Capex cost remain within existing £184m sanction, however this option would require utilisation of bulk of the contingency budget to deliver core scope, leaving £5m available to cover unexpected risk.
costs
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme.
b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010.
c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
headcount
A worst case scenario would see benefits delayed by 1-2 years, if the bulk of the headcount reduction cannot be achieved through normal turnover.
deployment
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
operational
Benefit realisation and people risk
The bulk of the Opex savings associated to the programme will be realised through improved effectiveness and efficiency of end to end processes, therefore less operational support, industrial and management staff will be required.
envisage
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
proactive
 Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
current electricity
The current Electricity Distribution price control review includes proposals for a customer service incentive that is likely to follow into the next Gas Distribution price control.
investment
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
mitigation
Mitigations
A strong risk reward and fixed fee elements will be included as part of the R2 and R3 supplier delivery contracts.
incorporate
The expenditure and savings associated with the programme will, subject to approval, be incorporated into the final version of the 2010 Gas Distribution business plan.
1.6
forecast
The total investment required to deliver the Gas Distribution Front Office programme has been updated from the forecast in the November 2009 National Grid Board paper now that we know the cost and value of the second and third releases.
system
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
integrated
The GDFO deployment will be integrated with the changes associated with the introduction of the new operating model to ensure a clear and consistent message is articulated.
8.3
cash flow
Investment Return
a) The return from this investment is based on pre-tax cash flows and includes regulatory impacts of the investments, severance and all Capex including Capex invested prior to March 2009.

Create a new Word List