Gas Distribution is committed to customer service excellence, prioritising it alongside safety and financial performance.
prioritise
Gas Distribution is committed to customer service excellence, prioritising it alongside safety and financial performance.
optimise
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
optimisation
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
decommission
Remaining investments are primarily driven by regulatory requirements or IS asset health upgrades.
d) £26m of Opex costs are required for archiving and decommissioning, incremental IS running costs that cannot be capitalised and activities required to implement business change.
programme
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
functionality
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
organisational
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value under ...
rationalisation
These include:
a) Contact Centre Strategy – Contact Centre rationalisation project, value circa £2m/year operating efficiencies and circa £6M/year property rationalisation. b) Customer Services Incentive – estimated +/- £12m. 8.
summarise
The options are summarised in the table below:
5.6
capitalise
Remaining investments are primarily driven by regulatory requirements or IS asset health upgrades.
d) £26m of Opex costs are required for archiving and decommissioning, incremental IS running costs that cannot be capitalised and activities required to implement business change.
grid
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
trend analysis
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analysis
incremental
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
severance
To deliver the full scope and benefits will require an additional investment of £21m Capex and £3.6m of severance.
workload
The deployment window is limited to a 7-month period from April and October to avoid peak Emergency and Repair workload during the winter.
handoff
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
standardise
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
integrate
The GDFO deployment will be integrated with the changes associated with the introduction of the new operating model to ensure a clear and consistent message is articulated.
8.3
maximise
The programme also seeks to deliver more effective controls, these are essential to ensure that business process performance is maximised, risks to business objectives are minimised and compliance obligations are met.
workflow
Other improvements include:
a) automation and reduction of labour intensive and inconsistently operated manual processes; b) a step change in the ease of field data capture through improved scripting and workflow on mobile devices; c) Improved data quality through system driven data cleanse prior to load into new systems suite.
scheduling
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
minimise
The programme has worked to reduce the impact of these increases and minimise the risk of future cost increases.
price control
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
update
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
distribution
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
information system
Therefore the following functionality would not be delivered:
Mobile geographical information system for the field force, this will result in the continued use of CD maps.
stabilisation
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
customer
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
deliver
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
automate
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
scope
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
implementation
Release 2 and 3 will have a phased deployment that mitigates the risk associated to big bang implementation events.
handover
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
automation
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
workforce
It will support work planning, scenario analysis and project management.
b) A Customer Relationship Management system (SAP CRM) coupled with leading Contact Centre technologies (Telephony, IVR, Voice recording, Workforce management).
utilisation
This will require manual paper based processes to address the lost of automation these solutions will deliver.
b) Cost impact – Capex cost remain within existing £184m sanction, however this option would require utilisation of bulk of the contingency budget to deliver core scope, leaving £5m available to cover unexpected risk.
costs
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
headcount
A worst case scenario would see benefits delayed by 1-2 years, if the bulk of the headcount reduction cannot be achieved through normal turnover.
deployment
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
operational
Benefit realisation and people risk
The bulk of the Opex savings associated to the programme will be realised through improved effectiveness and efficiency of end to end processes, therefore less operational support, industrial and management staff will be required.
envisage
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
proactive
Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
current electricity
The current Electricity Distribution price control review includes proposals for a customer service incentive that is likely to follow into the next Gas Distribution price control.
investment
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
mitigation
Mitigations
A strong risk reward and fixed fee elements will be included as part of the R2 and R3 supplier delivery contracts.
incorporate
The expenditure and savings associated with the programme will, subject to approval, be incorporated into the final version of the 2010 Gas Distribution business plan.
1.6
forecast
The total investment required to deliver the Gas Distribution Front Office programme has been updated from the forecast in the November 2009 National Grid Board paper now that we know the cost and value of the second and third releases.
system
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
integrated
The GDFO deployment will be integrated with the changes associated with the introduction of the new operating model to ensure a clear and consistent message is articulated.
8.3
cash flow
Investment Return
a) The return from this investment is based on pre-tax cash flows and includes regulatory impacts of the investments, severance and all Capex including Capex invested prior to March 2009.
gas
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
cost increase
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
standardisation
The programme is implementing Graphical design tools which will facilitate this standardisation, delivering £0.2m of Opex savings.
e) The ability to schedule teams efficiently between operating units and networks will drive further improvements in productivity.
benefit
To deliver the full scope and benefits will require an additional investment of £21m Capex and £3.6m of severance.
feedback
The principles, developed using market research, feedback from customers and their representatives set out our customers’ expectations.
cost
The total investment required to deliver the Gas Distribution Front Office programme has been updated from the forecast in the November 2009 National Grid Board paper now that we know the cost and value of the second and third releases.
release
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
include
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
data
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
stakeholder
This change will drive an increased focus on the efficient delivery of end to end processes, in order to better meet the needs and demands of customers and stakeholders.
4.3
datum
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
appendix
The table below sumarises the latest forecast of costs to deliver the scope that underpins the efficiency, customer and complaince benefits as described in the November Board paper (See appendix D).
replacement
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
configure
It should also be recognised that the new systems will offer the capability to configure additional work including alternative income earning work such as Smart metering unlike the restrictions with existing systems.
21.3
supportable
The existing systems have reached the end of their supportable life.
upgrade
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
communication channel
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
underpin
The table below sumarises the latest forecast of costs to deliver the scope that underpins the efficiency, customer and complaince benefits as described in the November Board paper (See appendix D).
productivity
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
dependant on
Additionally, it is widely recognised that the successful transformation of systems and processes is critically dependant on the level of acceptance by those impacted by it.
risk
The programme has worked to reduce the impact of these increases and minimise the risk of future cost increases.
process
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
option
Core scope and programme completion options
5.1
impact
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
regulatory
Regulatory risk
There is a risk that the measures that define success from a regulatory perspective will change as a result of GDPCR2.
implemented
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
schedule
The Gas Distribution Front Office programme schedule remains unchanged from the November 2009 Board paper.
reduction
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
solution
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
cost overrun
Option 1: Reduce scope and continue with existing budget
a) Description – Reduce the scope of Release 2 and 3 to ensure no cost overrun.
increase
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
delivery
Maintaining the scope will also enable the delivery of an additional £2.7m of Opex savings compared to November 2009 values.
contingency
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would require...
savings
Maintaining the scope will also enable the delivery of an additional £2.7m of Opex savings compared to November 2009 values.
ensure
Option 1: Reduce scope and continue with existing budget
a) Description – Reduce the scope of Release 2 and 3 to ensure no cost overrun.
methodology
On a risk score alone this investment would be deemed a priority project, scoring 45 out of a possible 49 using the National Grid’s risk scoring methodology on the basis that a critical IT system could fail for more than 24 hours in the next 3 years.
2.2
steering committee
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
require
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
standardised
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
sap
SAP, Click, ESRI and Syclo have been deployed to the field and back office for the whole of the Maintenance process and an Emergency pilot area.
2.2
breakdown
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
additional
To deliver the full scope and benefits will require an additional investment of £21m Capex and £3.6m of severance.
operate
To get best value from the investment and leverage additional value Gas Distribution has recently redesigned its operating model.
management
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
operating
To get best value from the investment and leverage additional value Gas Distribution has recently redesigned its operating model.
improvement
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
capability
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
existing
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
telephony
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
expenditure
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
sustainable
Sustainable execution risk
There is a risk that it is not possible to execute the required business changes to deliver Opex savings in a sustainable manner because the organisation is not equipped to deliver the level of change envisaged in the business case.
supplier
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
inbound
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analys...
facilitate
As shown Capex costs are set to exceed sanction, Opex costs are forecast to remain unchanged with Severance increases required to facilitate the delivery of expected benefits.
3.2
incorporated
The expenditure and savings associated with the programme will, subject to approval, be incorporated into the final version of the 2010 Gas Distribution business plan.
1.6
sign off
The scope of the IT systems to be replaced and enhanced through the Gas Distribution Front Office programme is described in Appendix A. This scope was signed off by the Programme Steering Group on the 9th June 2009.
3.2
improve
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
leveraging
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
economy of scale
Maintaining and upgrading an “evergreen” integrated system is cheaper when compared with replacing multiple separate systems over a similar period because of economies of scale and the avoidance of bespoke integration between systems.
3.5
deploy
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
implement
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
reduce
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
summary
Executive Summary
1.1
compliance
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
assumption
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
enhance
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
design
Business scope has been protected through design, build, test, and go live dates remain unchanged and additional benefits have been identified.
2.5
financial year
Consequential Opex savings of circa £1m are expected this financial year.
2.4
transformation
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
asset
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
control
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
handheld
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
incentive
This is particularly important for Gas Distribution as it prepares for the incentive/penalty regime associated to customer satisfaction performance that is likely to be introduced as part of the next price control.
6.
allocation
Our customers expect:
a) National Grid to do a great job – Improved capture of customer information including their needs, leading to improved job scheduling and work allocation.
replace
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
travel time
The new scheduling and dispatch capability and improved management information and reductions in wasted travel time are likely to have a positive impact on safety and environmental performance.
23.
sanction
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
graphical
The programme is implementing Graphical design tools which will facilitate this standardisation, delivering £0.2m of Opex savings.
e) The ability to schedule teams efficiently between operating units and networks will drive further improvements in productivity.
board meeting
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
procurement
The Capex sanction was subsequently increased by £6m to £48m to allow for early procurement of licences for the work scheduling and mobile device applications.
2.5
infrastructure
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
authorise
The creation of a single integrated suite of systems where data is stored in one place and is available as appropriate across all systems and to all users authorised to use it, will transform the work environment of employees.
front
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
mitigate
A delay of between 5 and 6 months is likely to cost £15m to £20m even after actions to mitigate costs have been taken.
overspend
On this basis it is anticipated that Ofgem will deem this investment efficient and therefore it will be incorporated into our RAV. It is only if our total Capex investment exceeds our allowance, which is not forecast to occur, that the licence indicates that the over spend will be subject to the IQI incentive, effectively reducing the Capex overspend incorporated into the RAV by 36%.
23.4
validation
Validation has continued with the latest view being incorporated in the latest Gas Distribution Business plan.
decision making
Robust data quality management processes to ensure the best information is used in decision making; and
d) Constraints on user access, limited to appropriate and authorised functions. 6.3
identified
Business scope has been protected through design, build, test, and go live dates remain unchanged and additional benefits have been identified.
2.5
outbound
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analys...
arbitrage
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
seamless
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multiple team...
office
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
licence
As a consequence, there will be a reduction in the utilisation of the Emergency FCO’s because of the need to maintain minimum staffing levels to discharge licence obligations.
business
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
mobile
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
aligning
In particular the objective to “become more efficient through transforming our operating model and increasingly aligning our processes.”
4.2
meter
Changes in the Metering market risk
There is a risk that the current forecast of metering workload over the life of the business plan/case is too high because smart metering roll out occurs more rapidly than expected.
achieve
This will be achieved using functionality within the Click Scheduling software, delivering a further £0.5m of savings.
validated
Additional benefits provide an additional £2.7m of Opex benefit and deliver an IRR of 15% and an incremental IRR of 22%.
c) Delivery Risk – Major suppliers have validated costs based on the scope of option 2, and will accept fixed price agreements for Release 2 and 3.
executive
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
analysis
Document management system and the Integration with the existing ETON (Street works notice system) and GBNA (Network Analysis Systems).
required
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
associate
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
support
They are prone to failure, are considered inadequate to support future business requirements.
organisation
Sustainable execution risk
There is a risk that it is not possible to execute the required business changes to deliver Opex savings in a sustainable manner because the organisation is not equipped to deliver the level of change envisaged in the business case.
spreadsheet
Investment Management solution, this will necessitate the continued use of multiple off line databases and spreadsheets to manage the investment plan and track delivery.
align
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisation to...
saving
Maintaining the scope will also enable the delivery of an additional £2.7m of Opex savings compared to November 2009 values.
efficiency
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
strategy
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
paper
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
integration
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
emergency
SAP, Click, ESRI and Syclo have been deployed to the field and back office for the whole of the Maintenance process and an Emergency pilot area.
2.2
core
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
improved
Benefit realisation and people risk
The bulk of the Opex savings associated to the programme will be realised through improved effectiveness and efficiency of end to end processes, therefore less operational support, industrial and management staff will be required.
Centre
These include:
a) Contact Centre Strategy – Contact Centre rationalisation project, value circa £2m/year operating efficiencies and circa £6M/year property rationalisation. b) Customer Services Incentive – estimated +/- £12m. 8.
approve
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
financial
A contingency of £7m is included within the forecast.
d) NOTE that John Pettigrew is the Programme Sponsor, and that Pete Massey, Director of Transformation, has the approved financial delegation to deliver the Programme. 2.
input
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
GPS
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
leverage
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
multiple
Investment Management solution, this will necessitate the continued use of multiple off line databases and spreadsheets to manage the investment plan and track delivery.
estimate
Initial estimates indicate that this would be in the range of £4-£6m of Capex.
steering
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
objective
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
database
Investment Management solution, this will necessitate the continued use of multiple off line databases and spreadsheets to manage the investment plan and track delivery.
disruption
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
identify
Business scope has been protected through design, build, test, and go live dates remain unchanged and additional benefits have been identified.
2.5
requirement
They are prone to failure, are considered inadequate to support future business requirements.
necessitate
Investment Management solution, this will necessitate the continued use of multiple off line databases and spreadsheets to manage the investment plan and track delivery.
April
The deployment window is limited to a 7-month period from April and October to avoid peak Emergency and Repair workload during the winter.
ageing
At that time a like for like replacement was envisaged would which would comprise £65m Capex and £14m Opex investment in tactical improvements to keep the ageing infrastructure operational.
geographic
This will eliminate manual processing associated with time sheeting and product ordering, data will be loaded directly into our core systems through the handheld device reducing errors allowing our field engineers to focus on job execution and customer service.
e) A best of breed geospatial information system (ESRI) to display a single accurate geographic view of asset and work information to the business in the field, operational support and customer services.
shoring
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
change
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
redesign
To get best value from the investment and leverage additional value Gas Distribution has recently redesigned its operating model.
information
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
productive
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
line of sight
National Grid recognises the importance of customer satisfaction in its vision and in its line of sight objectives.
enhanced
The scope of the IT systems to be replaced and enhanced through the Gas Distribution Front Office programme is described in Appendix A. This scope was signed off by the Programme Steering Group on the 9th June 2009.
3.2
submission
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
increased
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
current
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
impacted
Additionally, it is widely recognised that the successful transformation of systems and processes is critically dependant on the level of acceptance by those impacted by it.
model
To get best value from the investment and leverage additional value Gas Distribution has recently redesigned its operating model.
inconsistently
Other improvements include:
a) automation and reduction of labour intensive and inconsistently operated manual processes; b) a step change in the ease of field data capture through improved scripting and workflow on mobile devices; c) Improved data quality through system driven data cleanse prior to load into new systems suite.
click
SAP, Click, ESRI and Syclo have been deployed to the field and back office for the whole of the Maintenance process and an Emergency pilot area.
2.2
restructure
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value under ...
national
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
employee
There is a risk that poor employee engagement and trade union relationships will compromise the delivery of the required business changes adversely impacting the forecast savings.
will
To deliver the full scope and benefits will require an additional investment of £21m Capex and £3.6m of severance.
market research
The principles, developed using market research, feedback from customers and their representatives set out our customers’ expectations.
phase
Opex Summary
a) The following table summarises the proposed change in the phasing of Opex expenditure relative to the current sanction: 6.4
overrun
Option 1: Reduce scope and continue with existing budget
a) Description – Reduce the scope of Release 2 and 3 to ensure no cost overrun.
breed
The solution proposed comprises an integrated suite of IT systems centred on SAP and best of breed applications.
coincidental
This analysis will be repeated as part of each planning cycle to ensure benefits remain appropriately valued and aligned with coincidental initiatives and changes to the organisation.
7.2
framework
As detailed in the previous Board paper, programme capability has been designed to best support the business to:
a) Delight customers. b) Make life simpler for our people. c) Make us more productive. d) Provide a robust process and data control framework. 4.2
exist
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
realise
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
archive
Remaining investments are primarily driven by regulatory requirements or IS asset health upgrades.
d) £26m of Opex costs are required for archiving and decommissioning, incremental IS running costs that cannot be capitalised and activities required to implement business change.
level
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
component
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
project
The pre-tax IRR continues to exceed the anticipated 15% hurdle rate for IS projects and remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
reducing
Design work has already been undertaken for the components described in 1a), and consequently the cost of this element of the work will need to be written off, at a cost of between £4 and £6m.
c) Business benefit and return - £5 to £6m/annum of Opex benefits would be lost reducing the IRR to 14%.
manual
Automation of the management of work impacting consumers during major incidents, this will require continued use of the current manual paper based system.
complete
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
staff
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
approval
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
manage
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
scenario
It will support work planning, scenario analysis, project management improvements and drive consistency and data quality.
7.
authorised
The creation of a single integrated suite of systems where data is stored in one place and is available as appropriate across all systems and to all users authorised to use it, will transform the work environment of employees.
planning
This will be optimised through the use of the Click resource management tool being implemented for Repair in Release 3, and delivers a £0.6m benefit.
d) The creation of a standard set of planning tools to optimise designs will not only improve their quality but also significantly reduce rework.
sheeting
This will eliminate manual processing associated with time sheeting and product ordering, data will be loaded directly into our core systems through the handheld device reducing errors allowing our field engineers to focus on job execution and customer service.
e) A best of breed geospatial information system (ESRI) to display a single accurate geographic view of asset and work information to the business in the field, operational support and customer services.
enable
Maintaining the scope will also enable the delivery of an additional £2.7m of Opex savings compared to November 2009 values.
detailed
In particular, Release 3 which has only just moved into detailed design; resulting in an increase of £7m.
3.3
roll out
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
dependant
Additionally, it is widely recognised that the successful transformation of systems and processes is critically dependant on the level of acceptance by those impacted by it.
write off
Design work has already been undertaken for the components described in 1a), and consequently the cost of this element of the work will need to be written off, at a cost of between £4 and £6m.
c) Business benefit and return - £5 to £6m/annum of Opex benefits would be lost reducing the IRR to 14%.
November
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
capture
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
constraint
Given the budgetary constraints documented in section 3 there are two clear options for completing Release 2 and 3 of the programme.
5.3
interface
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
displacement
The high level assumption is that a significant proportion of all reductions in industrial staff, and operational support staff can be achieved through displacement of contractors/agency or retirement.
big bang
Release 2 and 3 will have a phased deployment that mitigates the risk associated to big bang implementation events.
continue
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
device
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
tactical
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
performance
As such planned benefits may be at risk because it may not be possible to implement all planned business changes due to constraints on performance.
included
A contingency of £7m is included within the forecast.
d) NOTE that John Pettigrew is the Programme Sponsor, and that Pete Massey, Director of Transformation, has the approved financial delegation to deliver the Programme. 2.
on-site
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
the like
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
anticipate
The pre-tax IRR continues to exceed the anticipated 15% hurdle rate for IS projects and remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
contractor
The high level assumption is that a significant proportion of all reductions in industrial staff, and operational support staff can be achieved through displacement of contractors/agency or retirement.
plan
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
repository
The new systems will create for the first time a single and complete asset repository that integrates asset information and the work required to maintain those assets.
sanctioned
Work on the programme was initially sanctioned in October 2008 at the Distribution Project Sanctioning Committee, and then subsequently approved by the Executive in April 2009.
a) The Executive paper estimated that the total investment required to deliver the programme was £145m Capex, £19m Opex and £24m of severance. b) In this paper the Executive sanctioned a further investment, £23.5m
compare
Maintaining the scope will also enable the delivery of an additional £2.7m of Opex savings compared to November 2009 values.
integrating
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment in in...
repair
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
remaining
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
rework
This will be optimised through the use of the Click resource management tool being implemented for Repair in Release 3, and delivers a £0.6m benefit.
d) The creation of a standard set of planning tools to optimise designs will not only improve their quality but also significantly reduce rework.
value
The total investment required to deliver the Gas Distribution Front Office programme has been updated from the forecast in the November 2009 National Grid Board paper now that we know the cost and value of the second and third releases.
sanctioning
Work on the programme was initially sanctioned in October 2008 at the Distribution Project Sanctioning Committee, and then subsequently approved by the Executive in April 2009.
a) The Executive paper estimated that the total investment required to deliver the programme was £145m Capex, £19m Opex and £24m of severance. b) In this paper the Executive sanctioned a further investment, £23.5m
centrally
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
work
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
operating cost
Benefits have been phased to minimise severance costs.
b) Business benefits are net of any increased operating costs, increased IS running costs are separately identified in the benefits table in 3.1. 26.3
adversely
There is a risk that poor employee engagement and trade union relationships will compromise the delivery of the required business changes adversely impacting the forecast savings.
budgetary
Given the budgetary constraints documented in section 3 there are two clear options for completing Release 2 and 3 of the programme.
5.3
unchanged
The Gas Distribution Front Office programme schedule remains unchanged from the November 2009 Board paper.
based
Automation of the management of work impacting consumers during major incidents, this will require continued use of the current manual paper based system.
price
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
vendor
Vendors have already reviewed the scope and have confirmed they can deliver in accordance with the current plan.
recognise
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
hurdle
The pre-tax IRR continues to exceed the anticipated 15% hurdle rate for IS projects and remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
realised
Benefit realisation and people risk
The bulk of the Opex savings associated to the programme will be realised through improved effectiveness and efficiency of end to end processes, therefore less operational support, industrial and management staff will be required.
bulk
This will require manual paper based processes to address the lost of automation these solutions will deliver.
b) Cost impact – Capex cost remain within existing £184m sanction, however this option would require utilisation of bulk of the contingency budget to deliver core scope, leaving £5m available to cover unexpected risk.
consequential
Consequential Opex savings of circa £1m are expected this financial year.
2.4
cleanse
Other improvements include:
a) automation and reduction of labour intensive and inconsistently operated manual processes; b) a step change in the ease of field data capture through improved scripting and workflow on mobile devices; c) Improved data quality through system driven data cleanse prior to load into new systems suite.
testing
Real data is being used in testing at an early stage to enable fixes to be implemented when the impact on the deployment date can be minimised.
8.2
delegation
A contingency of £7m is included within the forecast.
d) NOTE that John Pettigrew is the Programme Sponsor, and that Pete Massey, Director of Transformation, has the approved financial delegation to deliver the Programme. 2.
scoring
On a risk score alone this investment would be deemed a priority project, scoring 45 out of a possible 49 using the National Grid’s risk scoring methodology on the basis that a critical IT system could fail for more than 24 hours in the next 3 years.
2.2
eliminate
The additional Opex benefits are described below:
a) Automation of the handover of Emergency work between First Call Operatives and Repair teams, eliminating duplication of work.
provider
These providers were selected through a procurement exercise involving selection boards chaired by David Lister and Peter Massey including representatives from across the business.
3.4
graph
The following graph shows the annual pre-tax cash flows over the life of the front office systems which have been used to calculate the IRR for the investment.
28.2
board
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
efficiently
The programme is implementing Graphical design tools which will facilitate this standardisation, delivering £0.2m of Opex savings.
e) The ability to schedule teams efficiently between operating units and networks will drive further improvements in productivity.
suite
The current suite of front office systems supporting Maintenance, Emergency, Repair, Construction processes within UK Gas Distribution are becoming obsolete.
activity
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
safety
Gas Distribution is committed to customer service excellence, prioritising it alongside safety and financial performance.
duplication
The additional Opex benefits are described below:
a) Automation of the handover of Emergency work between First Call Operatives and Repair teams, eliminating duplication of work.
steer
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
significantly
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
executive director
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
devices
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
planned
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
total
The total investment required to deliver the Gas Distribution Front Office programme has been updated from the forecast in the November 2009 National Grid Board paper now that we know the cost and value of the second and third releases.
robust
As detailed in the previous Board paper, programme capability has been designed to best support the business to:
a) Delight customers. b) Make life simpler for our people. c) Make us more productive. d) Provide a robust process and data control framework. 4.2
tool
This will be optimised through the use of the Click resource management tool being implemented for Repair in Release 3, and delivers a £0.6m benefit.
d) The creation of a standard set of planning tools to optimise designs will not only improve their quality but also significantly reduce rework.
operative
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
resource
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
effectiveness
Benefit realisation and people risk
The bulk of the Opex savings associated to the programme will be realised through improved effectiveness and efficiency of end to end processes, therefore less operational support, industrial and management staff will be required.
additionally
Additionally, it is widely recognised that the successful transformation of systems and processes is critically dependant on the level of acceptance by those impacted by it.
aligned
This analysis will be repeated as part of each planning cycle to ensure benefits remain appropriately valued and aligned with coincidental initiatives and changes to the organisation.
7.2
engagement
There is a risk that poor employee engagement and trade union relationships will compromise the delivery of the required business changes adversely impacting the forecast savings.
environmental
Safety, Environmental and Planning Issues
22.1
automated
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
latest
The table below sumarises the latest forecast of costs to deliver the scope that underpins the efficiency, customer and complaince benefits as described in the November Board paper (See appendix D).
Price
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
focus on
This change will drive an increased focus on the efficient delivery of end to end processes, in order to better meet the needs and demands of customers and stakeholders.
4.3
new
The programme has trained more that 1000 people across 150 new procedures.
2.3
sponsor
A contingency of £7m is included within the forecast.
d) NOTE that John Pettigrew is the Programme Sponsor, and that Pete Massey, Director of Transformation, has the approved financial delegation to deliver the Programme. 2.
user
It is for this reason that the Gas Distribution Front Office Programme has made user engagement a key focus.
team
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
anticipated
The pre-tax IRR continues to exceed the anticipated 15% hurdle rate for IS projects and remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
following
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
describe
The table below sumarises the latest forecast of costs to deliver the scope that underpins the efficiency, customer and complaince benefits as described in the November Board paper (See appendix D).
disparate
There would be no operational performance benefits.
b) This solution would not deliver improvements in customer service. c) Although the initial investment is lower than the proposed investment, it gave a negative return of -1%. d) The disparate nature of the infrastructure would not be addressed and therefore more frequent and complex upgrades would continue to be required in future price controls.
application
The Capex sanction was subsequently increased by £6m to £48m to allow for early procurement of licences for the work scheduling and mobile device applications.
2.5
governance
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment i...
critically
Throughout the redesign business processes were critically examined and additional opportunities to leverage the GDFO systems were identified.
contact
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
invite
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
forecasting
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analys...
base
Automation of the management of work impacting consumers during major incidents, this will require continued use of the current manual paper based system.
below
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
alignment
The programme supports the Common Operating Model through its alignment with National Grid’s objectives.
subsequently
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
articulated
The GDFO deployment will be integrated with the changes associated with the introduction of the new operating model to ensure a clear and consistent message is articulated.
8.3
refresh
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
test
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
processed
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
comprise
The solution proposed comprises an integrated suite of IT systems centred on SAP and best of breed applications.
aggregate
The aggregate value of the recurring end state Opex benefits is 18.5% higher than the £27m base case (8/9 prices) in the April 2009 paper.
propose
Capex Summary
a) The following table summarises the proposed increase in Capex expenditure relative to the current sanction: 6.3
coupling
Systems will support close coupling of complaint and feedback information with intelligence drawn from MI to help drive process improvements.
stewardship
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment i...
limited
The deployment window is limited to a 7-month period from April and October to avoid peak Emergency and Repair workload during the winter.
approved
A contingency of £7m is included within the forecast.
d) NOTE that John Pettigrew is the Programme Sponsor, and that Pete Massey, Director of Transformation, has the approved financial delegation to deliver the Programme. 2.
field
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
Call
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
recommend
It is recommended that option 2 is pursued because it ensures that the programme delivers its full scope and:
a) Delivers an IRR of 15% and an incremental IRR of 22%. b) Secures the existing plus £2.7m of new value. c) Better supports the operating model as well as customer and compliance strategies. 6.
server
This is higher than the price control submission because of the incorporation of costs associated with aged servers which came to light afterwards.
19.
funding
Mitigations:
Submission of a Board Paper requesting additional funding to complete the programme based on Option 2. 8.5
primarily
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value under ...
provide
As detailed in the previous Board paper, programme capability has been designed to best support the business to:
a) Delight customers. b) Make life simpler for our people. c) Make us more productive. d) Provide a robust process and data control framework. 4.2
migrate
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment in integ...
communications
Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
annual
A further £2.7m of annual Opex benefits dependent on Release 2 and 3 GDFO capabilities were identified.
turnover
A worst case scenario would see benefits delayed by 1-2 years, if the bulk of the headcount reduction cannot be achieved through normal turnover.
closure
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value under ...
undertake
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
future
They are prone to failure, are considered inadequate to support future business requirements.
currently
This investment will mitigate the risk of system failure and address the increased cost of maintaining and modifying systems currently running beyond the end of their supportable life.
complexity
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
issue
Appendix C: Risks and Issues
8.1
dispatch
The best of breed systems chosen are “ESRI” for geographical information systems, “Click” for work scheduling and dispatch, and “Syclo” for field mobile devices.
3.3
configuration
The new configuration of IT systems to be delivered through the programme is illustrated below:
13.
through
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
Nelson
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
result
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
calculate
Costs to Achieve
a) Costs to achieve are predominantly severance and have been calculated based on analysis of the workforce’s age profile, and agency and contractor levels at a company level.
maintenance
SAP, Click, ESRI and Syclo have been deployed to the field and back office for the whole of the Maintenance process and an Emergency pilot area.
2.2
enquiry
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
focus
This change will drive an increased focus on the efficient delivery of end to end processes, in order to better meet the needs and demands of customers and stakeholders.
4.3
high-level
The productivity improvements enabled by the delivery of new Front Office systems were originally developed and subsequently valued through a series of workshops undertaken as part of the high-level design of the Gas Transformation Programme.
relative
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
consistent
The GDFO deployment will be integrated with the changes associated with the introduction of the new operating model to ensure a clear and consistent message is articulated.
8.3
key
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
minimum
As a consequence, there will be a reduction in the utilisation of the Emergency FCO’s because of the need to maintain minimum staffing levels to discharge licence obligations.
diagram
The diagrams below summarises the existing applications to be replaced:
15.
remain
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
coupled
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
interaction
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
case
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
described
The table below sumarises the latest forecast of costs to deliver the scope that underpins the efficiency, customer and complaince benefits as described in the November Board paper (See appendix D).
attributable
This analysis has only incorporated benefits directly attributable to the introduction of the new front office systems.
documented
Given the budgetary constraints documented in section 3 there are two clear options for completing Release 2 and 3 of the programme.
5.3
plus
Including items listed in section 5.3 a).
a) Cost impact – an additional investment of £21m Capex and £3m of severance costs (to cover additional efficiency benefits). b) Business benefit and return – Secures existing benefits plus supports the new operating model, customer and compliance strategies.
significant
Dependant on the workforce strategy adopted, the cost of severance will have a significant impact on the returns delivered by the programme.
invest
Mitigations:
The programme continues to invest heavily in its comprehensive approach to TU and employee engagement preparing the employees for the impact of the new systems.
Lister
These providers were selected through a procurement exercise involving selection boards chaired by David Lister and Peter Massey including representatives from across the business.
3.4
readiness
Change activities include: employee and TU engagement, location strategy, business readiness, changes to the safety case, post implementation support and training delivery.
e) The reason for the £19m increase in severance costs from the previous estimate of £24m is primarily because of severance associated with an additional reduction of 89 managers and senior staff not included in the April 2009 estimate. f) Although all non-critical work on Gas Distribution UK systems has been ...
e.g.
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
relationship
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
acceleration
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
Mark
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
incorporation
This is higher than the price control submission because of the incorporation of costs associated with aged servers which came to light afterwards.
19.
retirement
The high level assumption is that a significant proportion of all reductions in industrial staff, and operational support staff can be achieved through displacement of contractors/agency or retirement.
workshop
One example of this is creative workshops, known as ‘Design Theatres’, to help employees shape the design, ‘see the future’, and become advocates of the solution back in their part of the business.
5.
initial
Initial estimates indicate that this would be in the range of £4-£6m of Capex.
group
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
delegate
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
table
The table below includes a breakdown of expenditure relative to the current sanction, and a forecast of the remaining expenditure to complete the programme.
1.4
approximately
It is estimated that a 6 month delay could increase the cost of the programme by approximately £15 to £20m.
maintain
Maintaining the scope will also enable the delivery of an additional £2.7m of Opex savings compared to November 2009 values.
smart
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
third party
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
consequent
Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
efficient
This change will drive an increased focus on the efficient delivery of end to end processes, in order to better meet the needs and demands of customers and stakeholders.
4.3
geographical
Therefore the following functionality would not be delivered:
Mobile geographical information system for the field force, this will result in the continued use of CD maps.
delay
Overrun risk
There is a risk that Release 3 could slip 5 months into 2012 if there are any delays in either release 2 or 3 design build or test phases.
accurate
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analys...
tailored
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
dependent on
A further £2.7m of annual Opex benefits dependent on Release 2 and 3 GDFO capabilities were identified.
prone
They are prone to failure, are considered inadequate to support future business requirements.
exceed
As shown Capex costs are set to exceed sanction, Opex costs are forecast to remain unchanged with Severance increases required to facilitate the delivery of expected benefits.
3.2
recognised
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
detail
In particular, Release 3 which has only just moved into detailed design; resulting in an increase of £7m.
3.3
critical
A proportion of the £7m contingency is also available to be used at the discretion of the Steering Group for critical functionality.
8.4
service
Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
blueprint
These additional benefits, the operating model blueprint, customer, compliance strategies are dependent on the programme delivering the full scope.
5.
assume
Mitigations:
It is assumed that the current price control settlement will include arrangements to address the loss of meter work and the requirements for minimum staffing levels.
avoidance
Maintaining and upgrading an “evergreen” integrated system is cheaper when compared with replacing multiple separate systems over a similar period because of economies of scale and the avoidance of bespoke integration between systems.
3.5
communication
Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
come to light
This is higher than the price control submission because of the incorporation of costs associated with aged servers which came to light afterwards.
19.
adjustment
In addition a number of adjustments have been made which have increased confidence in the delivery of the value enabled by the programme.
inefficiency
Working with inconsistent data across multiple systems is a constant frustration and inefficiency.
6.2
introduction
The GDFO deployment will be integrated with the changes associated with the introduction of the new operating model to ensure a clear and consistent message is articulated.
8.3
completion
Core scope and programme completion options
5.1
realisation
Benefit realisation and people risk
The bulk of the Opex savings associated to the programme will be realised through improved effectiveness and efficiency of end to end processes, therefore less operational support, industrial and management staff will be required.
expertise
The main reasons for the movement in Capex costs are summarised below:
a) The April 2009 initial cost estimate was based on assumptions made at the time about deployment phasing and the level product specific expertise required to deliver the programme.
separately
This approach was taken because it is planned to decommission these systems as part of a wider rationalisation programme which will be managed separately from the Gas Distribution Front Office programme.
bespoke
Maintaining and upgrading an “evergreen” integrated system is cheaper when compared with replacing multiple separate systems over a similar period because of economies of scale and the avoidance of bespoke integration between systems.
3.5
senior
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value under ...
tax
The pre-tax IRR continues to exceed the anticipated 15% hurdle rate for IS projects and remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
effective
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
using
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
depreciation
Business Case Model Assumptions
a) RAV effective asset life = 45 years b) Financial depreciation on 20% reducing balance c) Pre-tax PCR return = 5.99% d) Post-tax PCR return = 4.94% e) IQI factor = 36%
centre
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
availability
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
inadequate
They are prone to failure, are considered inadequate to support future business requirements.
follow
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
available
This will require manual paper based processes to address the lost of automation these solutions will deliver.
b) Cost impact – Capex cost remain within existing £184m sanction, however this option would require utilisation of bulk of the contingency budget to deliver core scope, leaving £5m available to cover unexpected risk.
externally
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
transform
In particular the objective to “become more efficient through transforming our operating model and increasingly aligning our processes.”
4.2
pertinent
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
access
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
director
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
build
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
9th
The scope of the IT systems to be replaced and enhanced through the Gas Distribution Front Office programme is described in Appendix A. This scope was signed off by the Programme Steering Group on the 9th June 2009.
3.2
assumed
Mitigations:
It is assumed that the current price control settlement will include arrangements to address the loss of meter work and the requirements for minimum staffing levels.
comprehensive
Mitigations:
The programme continues to invest heavily in its comprehensive approach to TU and employee engagement preparing the employees for the impact of the new systems.
drive
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
assets
The new systems will create for the first time a single and complete asset repository that integrates asset information and the work required to maintain those assets.
use
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would require...
retrieve
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analysis; aut...
embedded
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls t...
predominantly
Costs to Achieve
a) Costs to achieve are predominantly severance and have been calculated based on analysis of the workforce’s age profile, and agency and contractor levels at a company level.
accountable
The Gas Distribution Front Office Programme Steering Group, chaired by Mark Fairbairn, oversees the programme; this group is accountable to the National Grid Executive.
3.
between
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
hub
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
agency
The high level assumption is that a significant proportion of all reductions in industrial staff, and operational support staff can be achieved through displacement of contractors/agency or retirement.
need
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
Cash
Pre-tax Cash Flows
28.1
intelligently
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls they rec...
para
(This estimate has been recently updated, Appendix B, para. 3).
define
Regulatory risk
There is a risk that the measures that define success from a regulatory perspective will change as a result of GDPCR2.
across
The programme has trained more that 1000 people across 150 new procedures.
2.3
embed
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls t...
execute
Sustainable execution risk
There is a risk that it is not possible to execute the required business changes to deliver Opex savings in a sustainable manner because the organisation is not equipped to deliver the level of change envisaged in the business case.
complex
Design and build risk
There is a risk that during the remaining design, build and test activities for Release 2 and 3 that more complex solutions will be required compared to current assumptions.
limit
The deployment window is limited to a 7-month period from April and October to avoid peak Emergency and Repair workload during the winter.
defining
This appendix summarises the scope of Gas Distribution Front Office by defining the systems to be replaced, and the new application landscape to be delivered.
like
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
address
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
operations
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
initiate
The Gas Distribution Front Office programme has been initiated to refresh and replace the existing UK Gas Distribution front office processes and systems.
end
The existing systems have reached the end of their supportable life.
valued
The productivity improvements enabled by the delivery of new Front Office systems were originally developed and subsequently valued through a series of workshops undertaken as part of the high-level design of the Gas Transformation Programme.
compatible
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
cleansing
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment in integ...
factor
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
15th
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
oversee
The Gas Distribution Front Office Programme Steering Group, chaired by Mark Fairbairn, oversees the programme; this group is accountable to the National Grid Executive.
3.
delight
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
manager
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value under ...
remit
Mitigations:
The new Operating Model with its focus on end to end processes includes as part of its remit to underpin the savings delivered through new systems such as the Gas Distribution Front Office programme.
training
The remaining expenditure covers completion of detailed design, systems build, testing, training and deployment of each release plus technical infrastructure costs.
2.6
committee
National Grid plc
Executive Committee UK Gas Distribution Front Office Update A paper by Mark Fairbairn, Executive Director, Gas Distribution 1.
obligation
As a consequence, there will be a reduction in the utilisation of the Emergency FCO’s because of the need to maintain minimum staffing levels to discharge licence obligations.
appropriately
This analysis will be repeated as part of each planning cycle to ensure benefits remain appropriately valued and aligned with coincidental initiatives and changes to the organisation.
7.2
autumn
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
offshore
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
intensive
Other improvements include:
a) automation and reduction of labour intensive and inconsistently operated manual processes; b) a step change in the ease of field data capture through improved scripting and workflow on mobile devices; c) Improved data quality through system driven data cleanse prior to load into new systems suite.
processing
This will eliminate manual processing associated with time sheeting and product ordering, data will be loaded directly into our core systems through the handheld device reducing errors allowing our field engineers to focus on job execution and customer service.
e) A best of breed geospatial information system (ESRI) to display a single accurate geographic view of asset and work information to the business in the field, operational support and customer services.
network
The programme is implementing Graphical design tools which will facilitate this standardisation, delivering £0.2m of Opex savings.
e) The ability to schedule teams efficiently between operating units and networks will drive further improvements in productivity.
failure
They are prone to failure, are considered inadequate to support future business requirements.
job
Our customers expect:
a) National Grid to do a great job – Improved capture of customer information including their needs, leading to improved job scheduling and work allocation.
month
Overrun risk
There is a risk that Release 3 could slip 5 months into 2012 if there are any delays in either release 2 or 3 design build or test phases.
cash
Investment Return
a) The return from this investment is based on pre-tax cash flows and includes regulatory impacts of the investments, severance and all Capex including Capex invested prior to March 2009.
addition
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
satisfaction
National Grid recognises the importance of customer satisfaction in its vision and in its line of sight objectives.
uncertainty
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
recommendation
Recommendation
6.1
adherence
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analys...
leading
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
recurring
The aggregate value of the recurring end state Opex benefits is 18.5% higher than the £27m base case (8/9 prices) in the April 2009 paper.
expected
Consequential Opex savings of circa £1m are expected this financial year.
2.4
initially
Work on the programme was initially sanctioned in October 2008 at the Distribution Project Sanctioning Committee, and then subsequently approved by the Executive in April 2009.
a) The Executive paper estimated that the total investment required to deliver the programme was £145m Capex, £19m Opex and £24m of severance. b) In this paper the Executive sanctioned a further investment, £23.5m
previous
As detailed in the previous Board paper, programme capability has been designed to best support the business to:
a) Delight customers. b) Make life simpler for our people. c) Make us more productive. d) Provide a robust process and data control framework. 4.2
location
Change activities include: employee and TU engagement, location strategy, business readiness, changes to the safety case, post implementation support and training delivery.
e) The reason for the £19m increase in severance costs from the previous estimate of £24m is primarily because of severance associated with an additional reduction of 89 managers and senior staff not included in the April 2009 estimate. f) Although all non-critical work on Gas Distribution UK systems has been ...
develop
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
trade union
There is a risk that poor employee engagement and trade union relationships will compromise the delivery of the required business changes adversely impacting the forecast savings.
web
Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
procedure
The programme has trained more that 1000 people across 150 new procedures.
2.3
work on
Work on the programme was initially sanctioned in October 2008 at the Distribution Project Sanctioning Committee, and then subsequently approved by the Executive in April 2009.
a) The Executive paper estimated that the total investment required to deliver the programme was £145m Capex, £19m Opex and £24m of severance. b) In this paper the Executive sanctioned a further investment, £23.5m
consequently
Design work has already been undertaken for the components described in 1a), and consequently the cost of this element of the work will need to be written off, at a cost of between £4 and £6m.
c) Business benefit and return - £5 to £6m/annum of Opex benefits would be lost reducing the IRR to 14%.
only if
On this basis it is anticipated that Ofgem will deem this investment efficient and therefore it will be incorporated into our RAV. It is only if our total Capex investment exceeds our allowance, which is not forecast to occur, that the licence indicates that the over spend will be subject to the IQI incentive, effectively reducing the Capex overspend incorporated into the RAV by 36%.
23.4
reflect
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value...
complaint
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
assess
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls they rec...
driven
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
further
A further £2.7m of annual Opex benefits dependent on Release 2 and 3 GDFO capabilities were identified.
execution
Sustainable execution risk
There is a risk that it is not possible to execute the required business changes to deliver Opex savings in a sustainable manner because the organisation is not equipped to deliver the level of change envisaged in the business case.
bespeak
Maintaining and upgrading an “evergreen” integrated system is cheaper when compared with replacing multiple separate systems over a similar period because of economies of scale and the avoidance of bespoke integration between systems.
3.5
single
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multiple team...
best
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
accordance
Vendors have already reviewed the scope and have confirmed they can deliver in accordance with the current plan.
investigation
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
quality
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
in place
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
allowance
The capital investment of £157m exceeds the £79m allowance submitted at the time of the price control.
industrial
Benefit realisation and people risk
The bulk of the Opex savings associated to the programme will be realised through improved effectiveness and efficiency of end to end processes, therefore less operational support, industrial and management staff will be required.
balance
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value...
budget
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
evergreen
Maintaining and upgrading an “evergreen” integrated system is cheaper when compared with replacing multiple separate systems over a similar period because of economies of scale and the avoidance of bespoke integration between systems.
3.5
criterion
To ensure the programme delivers the expected transformation three key criterion are being applied to all elements of the process and system solution:
a) Will it delight our customers? b) Will it make life simpler for our people? c) Will it make us more productive? 4.3
margin
The National Grid Board is invited to:
a) APPROVE the remaining investment of £112m Capex, £24m Opex, and £43m of severance costs in the range +/- 10% to deliver the Gas Front Office Programme. b) DELEGATE authority to the National Grid Executive Committee for the programme including changes to scope and expenditure that would require the use of the 10% risk margin. c) NOTE that Mark Fairbairn is the Programme Sponsor, and that Pete Massey, Director of Transformation, has the appro...
supporting
The current suite of front office systems supporting Maintenance, Emergency, Repair, Construction processes within UK Gas Distribution are becoming obsolete.
hourly
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
replacing
Maintaining and upgrading an “evergreen” integrated system is cheaper when compared with replacing multiple separate systems over a similar period because of economies of scale and the avoidance of bespoke integration between systems.
3.5
negative
The incremental IRR, the IRR of the difference in cash flows between the recommended solution and the like for like solution, is 24%.
c) A 10% reduction in benefits plus a 10% increase in Capex costs would reduce the IRR to 13% and reduce the incremental IRR to 20%. d) The limited Opex benefits delivered by the like for like option would result in a negative return of -1%.
prior
Other improvements include:
a) automation and reduction of labour intensive and inconsistently operated manual processes; b) a step change in the ease of field data capture through improved scripting and workflow on mobile devices; c) Improved data quality through system driven data cleanse prior to load into new systems suite.
running
This investment will mitigate the risk of system failure and address the increased cost of maintaining and modifying systems currently running beyond the end of their supportable life.
enabling
The best of breed systems, built on the foundations of SAP capability and data, are critical to enabling the programme Opex benefits.
likely
The cost of delivering de-scoped capability at a later date is likely to be higher than the cost of delivering through existing GDFO programme given set up costs and overheads.
annum
Design work has already been undertaken for the components described in 1a), and consequently the cost of this element of the work will need to be written off, at a cost of between £4 and £6m.
c) Business benefit and return - £5 to £6m/annum of Opex benefits would be lost reducing the IRR to 14%.
in particular
In particular, Release 3 which has only just moved into detailed design; resulting in an increase of £7m.
3.3
lead
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
range
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
fix
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
flow
Investment Return
a) The return from this investment is based on pre-tax cash flows and includes regulatory impacts of the investments, severance and all Capex including Capex invested prior to March 2009.
within
A contingency of £7m is included within the forecast.
d) NOTE that John Pettigrew is the Programme Sponsor, and that Pete Massey, Director of Transformation, has the approved financial delegation to deliver the Programme. 2.
life
The existing systems have reached the end of their supportable life.
1000
The programme has trained more that 1000 people across 150 new procedures.
2.3
articulate
The GDFO deployment will be integrated with the changes associated with the introduction of the new operating model to ensure a clear and consistent message is articulated.
8.3
frustration
Working with inconsistent data across multiple systems is a constant frustration and inefficiency.
6.2
review
Vendors have already reviewed the scope and have confirmed they can deliver in accordance with the current plan.
potentially
Consequently a delay in the design, build or testing phases will put at risk the deployment and potentially result in the programme slipping 6 months with consequent cost implications.
pipeline
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
possible
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
completing
Given the budgetary constraints documented in section 3 there are two clear options for completing Release 2 and 3 of the programme.
5.3
decision
Robust data quality management processes to ensure the best information is used in decision making; and
d) Constraints on user access, limited to appropriate and authorised functions. 6.3
allow for
The Capex sanction was subsequently increased by £6m to £48m to allow for early procurement of licences for the work scheduling and mobile device applications.
2.5
expect
Consequential Opex savings of circa £1m are expected this financial year.
2.4
environment
The creation of a single integrated suite of systems where data is stored in one place and is available as appropriate across all systems and to all users authorised to use it, will transform the work environment of employees.
dependent
A further £2.7m of annual Opex benefits dependent on Release 2 and 3 GDFO capabilities were identified.
appropriate
The creation of a single integrated suite of systems where data is stored in one place and is available as appropriate across all systems and to all users authorised to use it, will transform the work environment of employees.
technology
It will support work planning, scenario analysis and project management.
b) A Customer Relationship Management system (SAP CRM) coupled with leading Contact Centre technologies (Telephony, IVR, Voice recording, Workforce management).
nominal
A simple like for like replacement was envisaged at the time and £65m Capex and £14m Opex (nominal) was included in Gas Distribution’s submission.
reduced
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
used
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
fixed
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
alternative
It should also be recognised that the new systems will offer the capability to configure additional work including alternative income earning work such as Smart metering unlike the restrictions with existing systems.
21.3
write down
Writing off design costs
There is a risk that any reduction in the scope of Release 2 and 3 will necessitate the writing down of design costs for functionality that does not form part of the next two Releases.
successfully
The Gas Distribution Front Office programme has successfully implemented the first of three releases to refresh and replace the existing UK Gas Distribution front office systems.
timely
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
submit
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
discharge
As a consequence, there will be a reduction in the utilisation of the Emergency FCO’s because of the need to maintain minimum staffing levels to discharge licence obligations.
more
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
consistency
It will support work planning, scenario analysis, project management improvements and drive consistency and data quality.
7.
basis
On a risk score alone this investment would be deemed a priority project, scoring 45 out of a possible 49 using the National Grid’s risk scoring methodology on the basis that a critical IT system could fail for more than 24 hours in the next 3 years.
2.2
obsolete
The current suite of front office systems supporting Maintenance, Emergency, Repair, Construction processes within UK Gas Distribution are becoming obsolete.
flexible
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
inform
Specific process and control issues arising from the Project Nelson investigation are actively being used to inform the design.
4.4
specific
Specific process and control issues arising from the Project Nelson investigation are actively being used to inform the design.
4.4
developed
Integrated end state design is complete covering all processes and systems, key vendors have been engaged, licences for all major systems have been procured and programme methodology developed with supporting tools in place.
full
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
retain
Option 2: Increase Capex investment by £21m to deliver complete scope
a) Description - Retain full business scope in Release 2 and 3.
software
This will be achieved using functionality within the Click Scheduling software, delivering a further £0.5m of savings.
distribute
Aggregating and distributing accurate management information to support more effective and informed decision making.
proportion
A proportion of the £7m contingency is also available to be used at the discretion of the Steering Group for critical functionality.
8.4
progress
The purpose of this paper is to update the Group Executive on progress of the Gas Distribution Front Office programme since the November 2009 Board paper and to gain approval for an increase in the investment required to complete the full business scope of the programme.
1.2
October
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
part
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
Mobile
Therefore the following functionality would not be delivered:
Mobile geographical information system for the field force, this will result in the continued use of CD maps.
cover
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
actively
Specific process and control issues arising from the Project Nelson investigation are actively being used to inform the design.
4.4
grade
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value under ...
approach
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
non
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
return
Design work has already been undertaken for the components described in 1a), and consequently the cost of this element of the work will need to be written off, at a cost of between £4 and £6m.
c) Business benefit and return - £5 to £6m/annum of Opex benefits would be lost reducing the IRR to 14%.
listed
Including items listed in section 5.3 a).
a) Cost impact – an additional investment of £21m Capex and £3m of severance costs (to cover additional efficiency benefits). b) Business benefit and return – Secures existing benefits plus supports the new operating model, customer and compliance strategies.
operation
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
portal
Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
relate
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analysis; aut...
higher
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
informed
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
guiding
The systems design and process refresh have been guided by Gas Distribution’s customer strategy and its 5 guiding principles.
score
On a risk score alone this investment would be deemed a priority project, scoring 45 out of a possible 49 using the National Grid’s risk scoring methodology on the basis that a critical IT system could fail for more than 24 hours in the next 3 years.
2.2
reward
Mitigations
A strong risk reward and fixed fee elements will be included as part of the R2 and R3 supplier delivery contracts.
consumer
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
consistently
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analysis; aut...
prepare for
This is particularly important for Gas Distribution as it prepares for the incentive/penalty regime associated to customer satisfaction performance that is likely to be introduced as part of the next price control.
6.
note
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
tight
This would also adversly impact customer service, and the level of streetworks and compensation payments.
d) Delivery Risk – This option includes a contingency of £5m which is tight for a programme of this size.
make
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
inconsistent
Working with inconsistent data across multiple systems is a constant frustration and inefficiency.
6.2
peak
The deployment window is limited to a 7-month period from April and October to avoid peak Emergency and Repair workload during the winter.
indicate
Initial estimates indicate that this would be in the range of £4-£6m of Capex.
built
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
warehouse
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment i...
implication
Consequently a delay in the design, build or testing phases will put at risk the deployment and potentially result in the programme slipping 6 months with consequent cost implications.
continued
Therefore the following functionality would not be delivered:
Mobile geographical information system for the field force, this will result in the continued use of CD maps.
making
This performance improvement is described by three clear objectives:
a) Delighting customers b) Making life simpler for our people c) Making us more productive This performance improvement will be underpinned by a robust process and data control framework. 2.4
train
The programme has trained more that 1000 people across 150 new procedures.
2.3
positive
The new scheduling and dispatch capability and improved management information and reductions in wasted travel time are likely to have a positive impact on safety and environmental performance.
23.
negotiate
Mitigations:
The fixed price risk reward framework being negotiated with suppliers will share this risk with suppliers who will be required to absorb any overruns.
priority
On a risk score alone this investment would be deemed a priority project, scoring 45 out of a possible 49 using the National Grid’s risk scoring methodology on the basis that a critical IT system could fail for more than 24 hours in the next 3 years.
2.2
move into
In particular, Release 3 which has only just moved into detailed design; resulting in an increase of £7m.
3.3
exclude
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment i...
unit
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
element
Design work has already been undertaken for the components described in 1a), and consequently the cost of this element of the work will need to be written off, at a cost of between £4 and £6m.
c) Business benefit and return - £5 to £6m/annum of Opex benefits would be lost reducing the IRR to 14%.
track
Investment Management solution, this will necessitate the continued use of multiple off line databases and spreadsheets to manage the investment plan and track delivery.
action
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
transfer
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
couple
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
standard
This will be optimised through the use of the Click resource management tool being implemented for Repair in Release 3, and delivers a £0.6m benefit.
d) The creation of a standard set of planning tools to optimise designs will not only improve their quality but also significantly reduce rework.
lower
The use of an integrated SAP solution is expected to deliver lower IS Capex in future years.
final
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
creation
This will be optimised through the use of the Click resource management tool being implemented for Repair in Release 3, and delivers a £0.6m benefit.
d) The creation of a standard set of planning tools to optimise designs will not only improve their quality but also significantly reduce rework.
adjusted
The requirement to replace these systems was identified at the time of the last price control, and £65m Capex and £14m Opex (adjusted for inflation) was included in National Grid’s submission.
used to
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
prepare
Mitigations:
The programme continues to invest heavily in its comprehensive approach to TU and employee engagement preparing the employees for the impact of the new systems.
legacy
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
deem
On a risk score alone this investment would be deemed a priority project, scoring 45 out of a possible 49 using the National Grid’s risk scoring methodology on the basis that a critical IT system could fail for more than 24 hours in the next 3 years.
2.2
remains
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
links
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls t...
major
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
perspective
Regulatory risk
There is a risk that the measures that define success from a regulatory perspective will change as a result of GDPCR2.
script
Other improvements include:
a) automation and reduction of labour intensive and inconsistently operated manual processes; b) a step change in the ease of field data capture through improved scripting and workflow on mobile devices; c) Improved data quality through system driven data cleanse prior to load into new systems suite.
build on
The best of breed systems, built on the foundations of SAP capability and data, are critical to enabling the programme Opex benefits.
also
Maintaining the scope will also enable the delivery of an additional £2.7m of Opex savings compared to November 2009 values.
explore
This option was explored in more detail in the April 2009 paper and is summarised in Appendix B.
2.3
link
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls t...
recur
The aggregate value of the recurring end state Opex benefits is 18.5% higher than the £27m base case (8/9 prices) in the April 2009 paper.
payment
This would also adversly impact customer service, and the level of streetworks and compensation payments.
d) Delivery Risk – This option includes a contingency of £5m which is tight for a programme of this size.
engineer
In addition, customer information pertinent to a job will be passed to field engineers via their handheld device to improve customer interactions.
e) To see improvement actions as a result of feedback – The solution will facilitate proactive feedback, capture inputs from customers which will be held centrally and processed in a system driven and standardised fashion.
defer
To deliver further savings the replacment of one or more core systems would have to be defered.
5.4
conjunction
New front office systems in conjunction with the customer strategy will place Gas Distribution in a strong position to respond to any regulatory incentives.
23.3
completed
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multiple team...
authority
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
dictate
Detailed design for each release will dictate the precise extent to which this functionality will actually be delivered and consequently the benefits realised.
27.3
designed
As detailed in the previous Board paper, programme capability has been designed to best support the business to:
a) Delight customers. b) Make life simpler for our people. c) Make us more productive. d) Provide a robust process and data control framework. 4.2
respectively
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
create
The requirement to replace front office IT systems has created the opportunity for Gas Distribution in the UK to progress the Common Operating Model by automating business processes to deliver a sustained improvement in performance.
ordering
This will eliminate manual processing associated with time sheeting and product ordering, data will be loaded directly into our core systems through the handheld device reducing errors allowing our field engineers to focus on job execution and customer service.
e) A best of breed geospatial information system (ESRI) to display a single accurate geographic view of asset and work information to the business in the field, operational support and customer services.
theatre
Design theatres, acceleration weeks, and on and offshore design hubs have been used to improve the quality and efficiency of design work.
3.
effectively
On this basis it is anticipated that Ofgem will deem this investment efficient and therefore it will be incorporated into our RAV. It is only if our total Capex investment exceeds our allowance, which is not forecast to occur, that the licence indicates that the over spend will be subject to the IQI incentive, effectively reducing the Capex overspend incorporated into the RAV by 36%.
23.4
function
Robust data quality management processes to ensure the best information is used in decision making; and
d) Constraints on user access, limited to appropriate and authorised functions. 6.3
reflecting
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value...
elements
Mitigations
A strong risk reward and fixed fee elements will be included as part of the R2 and R3 supplier delivery contracts.
profile
Costs to Achieve
a) Costs to achieve are predominantly severance and have been calculated based on analysis of the workforce’s age profile, and agency and contractor levels at a company level.
slipping
Consequently a delay in the design, build or testing phases will put at risk the deployment and potentially result in the programme slipping 6 months with consequent cost implications.
construction
The purpose of this paper is to seek approval for the remaining expenditure to complete the construction and implementation of the new organisation, processes and IT systems required to deliver programme scope.
document
Given the budgetary constraints documented in section 3 there are two clear options for completing Release 2 and 3 of the programme.
5.3
extend
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
time
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
consequence
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
expanded
This together with greater confidence in the accuracy of the forecast expenditure has increased total Capex by approximately £20m.
b) Scope of the programme has expanded to include additional projects such as Smart Travel and additional process and data controls work.
demonstrate
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
date
Business scope has been protected through design, build, test, and go live dates remain unchanged and additional benefits have been identified.
2.5
specialist
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the...
projected
Cost Summary
a) The table below provides the cost summary for the Gas Distribution Front Office Programme. b) The future projected Capex costs of £112m cover all work to deliver all three releases of the Gas Distribution Front Office programme summarised in 3.5. c) The Gas Distribution Front Office Capex represents bulk of planned UK Gas Distribution IS Capex investment during the life of the programme.
channels
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
consultation
Business Opex
a) Includes the following activities: a) Incremental IS running costs during the programme that cannot be capitalised. b) Archiving and decommissioning costs. c) Organisation design, HR strategy, employee/TU consultation and engagement. d) Training of 4,500 employees. e) Changes to safety case, polices and procedures. f) Business readiness, post implementation support and testing. 26.2
essential
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
recording
It will support work planning, scenario analysis and project management.
b) A Customer Relationship Management system (SAP CRM) coupled with leading Contact Centre technologies (Telephony, IVR, Voice recording, Workforce management).
acceptable
This option also includes an acceptable level of contingency required given risk associated with the remiander of the programme.
5.5
tested
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
balanced
These adjustments are summarised below with a more detailed breakdown of the benefits by process in Appendix D:
a) The value of Opex benefits are more balanced across the processes than before, reflecting updated forecasts of lower meter workload within the Emergency process and additional value identified in other processes. b) A small number of additional Repex benefits have been identified; however these have a limited effect because it is only possible to retain 36% of the value...
consider
They are prone to failure, are considered inadequate to support future business requirements.
signed
The scope of the IT systems to be replaced and enhanced through the Gas Distribution Front Office programme is described in Appendix A. This scope was signed off by the Programme Steering Group on the 9th June 2009.
3.2
quotation
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
overall
This number has been updated to reflect a lower overall costs during the programme and a change to the treatment of the expenditure; The impact is a reduction in Capex of £10m and an increase in Opex of £5m.
25.2
initiative
This analysis will be repeated as part of each planning cycle to ensure benefits remain appropriately valued and aligned with coincidental initiatives and changes to the organisation.
7.2
cycle
This analysis will be repeated as part of each planning cycle to ensure benefits remain appropriately valued and aligned with coincidental initiatives and changes to the organisation.
7.2
Apollo
Apollo upgrade (infrastructure that manages the interface between core systems and field devices) and the stabilisation of the existing TEAR system, which holds Gas Distribution pipeline records, to extend its life until it is replaced as part of Release 3.
c) Increased complexity, this increase results from higher levels of systems integration and new control requirements following the Nelson investigation that were not apparent until Release 2 and 3 design.
any
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would require...
demonstrated
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
scheduled
The Gas Distribution Front Office programme is currently scheduled to run from March 2009 until January 2012.
loss
Customer web portal, proactive customer communications and correspondence letters, leading to the consequent loss of customer service improvements.
strategic
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment i...
fee
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
related to
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analysis; aut...
opportunity
Throughout the redesign business processes were critically examined and additional opportunities to leverage the GDFO systems were identified.
applied
To ensure the programme delivers the expected transformation three key criterion are being applied to all elements of the process and system solution:
a) Will it delight our customers? b) Will it make life simpler for our people? c) Will it make us more productive? 4.3
December
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
accuracy
This together with greater confidence in the accuracy of the forecast expenditure has increased total Capex by approximately £20m.
b) Scope of the programme has expanded to include additional projects such as Smart Travel and additional process and data controls work.
addressed
There would be no operational performance benefits.
b) This solution would not deliver improvements in customer service. c) Although the initial investment is lower than the proposed investment, it gave a negative return of -1%. d) The disparate nature of the infrastructure would not be addressed and therefore more frequent and complex upgrades would continue to be required in future price controls.
post
Change activities include: employee and TU engagement, location strategy, business readiness, changes to the safety case, post implementation support and training delivery.
e) The reason for the £19m increase in severance costs from the previous estimate of £24m is primarily because of severance associated with an additional reduction of 89 managers and senior staff not included in the April 2009 estimate. f) Although all non-critical work on Gas Distribution UK systems has been ...
combine
When the Opex benefits are combined with the increased Capex and Opex costs, the IRR is 16% (down 1%).
reporting
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment in integ...
incident
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
ability
Automation of the handover of Emergency work between First Call Operatives and Repair teams (compliance), the ability to automate the management of work impacting consumers during major incidents (customer and business case)
b) Tactical investments, these investments have been needed to core IS legacy systems to either extend their life, or upgrade a company system to make it compatible with GDFO systems; resulting in an increase of £2m. e.g.
considered
They are prone to failure, are considered inadequate to support future business requirements.
creative
One example of this is creative workshops, known as ‘Design Theatres’, to help employees shape the design, ‘see the future’, and become advocates of the solution back in their part of the business.
5.
Best
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment i...
roll
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
labour
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
handling
This solution was not recommended in April 2009 because
a) The improvement in cost efficiency would be limited to savings in some centre and operational support savings where manual handling of the data would be eliminated (£1m/year).
illustrate
The new configuration of IT systems to be delivered through the programme is illustrated below:
13.
pitched
Benefits across all processes have been pitched at mid case level, and along with a better balance across Gas Distribution, this risk is now reduced.
stretching
Execution Risk
a) The plan to complete the Gas Distribution Front Office programme in two and half years is particularly stretching because the deployment window is very tight, limited to a 6-month period between April and September, if we avoid the peak operational workload months.
trend
These systems will manage all inbound and outbound customer communications; capture, manage and provide access to customer data; manage customer handoffs across end to end processes; track and manage adherence to customer standards of service.
c) A best of breed work scheduling and dispatch application (Click) to provide improvements in centre, operational support and field productivity through; more accurate forecasting of work using historical data, external input and trend analys...
compensation
This would also adversly impact customer service, and the level of streetworks and compensation payments.
d) Delivery Risk – This option includes a contingency of £5m which is tight for a programme of this size.
run
This investment will mitigate the risk of system failure and address the increased cost of maintaining and modifying systems currently running beyond the end of their supportable life.
calculation
Severance Assumptions
a) Operations and Distribution Customer Support – A significant proportion of reductions will be achieved through retirement, displacement of contractors/agency staff and transfers to alternative work. b) Senior staff and managers – 100% of the reduction would require severance. c) Costs based on severance paid in previous 12 months. d) The following table shows the current assumed breakdown of FTE’s in the severance calculation. 27.
people
The objective of the programme continues to be to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.3
restriction
It should also be recognised that the new systems will offer the capability to configure additional work including alternative income earning work such as Smart metering unlike the restrictions with existing systems.
21.3
discretion
A proportion of the £7m contingency is also available to be used at the discretion of the Steering Group for critical functionality.
8.4
tailor
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
year
Consequential Opex savings of circa £1m are expected this financial year.
2.4
secure
Including items listed in section 5.3 a).
a) Cost impact – an additional investment of £21m Capex and £3m of severance costs (to cover additional efficiency benefits). b) Business benefit and return – Secures existing benefits plus supports the new operating model, customer and compliance strategies.
acceptance
Additionally, it is widely recognised that the successful transformation of systems and processes is critically dependant on the level of acceptance by those impacted by it.
travel
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
off
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
summer
Release 1 was delivered as planned in October 2010, with Release 2 and 3 on schedule for deployment in through summer 2011 and autumn 2011 respectively.
2.1
preference
Multiple customer communication channels that can be tailored to their preferences, such as enhanced web capability to support customer enquiries and complaints.
c) National Grid to minimise disruptions – Improvements in and automation of the handoffs between teams and communications from field to customer service and support, coupled with increased efficiency in the scheduling and dispatch of work, will help to minimise disruption to customers for whom work is undertaken by multip...
precise
Detailed design for each release will dictate the precise extent to which this functionality will actually be delivered and consequently the benefits realised.
27.3
delayed
A worst case scenario would see benefits delayed by 1-2 years, if the bulk of the headcount reduction cannot be achieved through normal turnover.
excessive
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls t...
developing
This automation is made possible by the capture and transfer between teams, of On-Site Gas Emergency Management information and delivers £0.6m of value.
b) Operations are developing new flexible work patterns, (e.g. annual hours, Winter/Summer) that GDFO will optimise and enable through the Click Scheduling solution, realising an additional £0.8m. c) Optimisation of the Repair teams allowing them to undertake increased levels of Repex, in place of Opex work.
excellence
Gas Distribution is committed to customer service excellence, prioritising it alongside safety and financial performance.
extension
This like for like solution would exclude the following functionality compared with the full solution proposed in this paper:
a) Extended SAP functionality including Strategic Enterprise Management, Customer Relationship Management, and Business Warehouse. b) Best of breed scheduling, GIS and mobile technology. c) Extension of the geographic information system to integrate with the key components of the solution. d) Data stewardship, readiness and governance including investment i...
early
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
values
Maintaining the scope will also enable the delivery of an additional £2.7m of Opex savings compared to November 2009 values.
technique
The programme approach has been recognised externally as industry leading, it has been carefully constructed, leveraging the best of methods and techniques from various support partners, E&Y, SAP, and Wipro.
help
One example of this is creative workshops, known as ‘Design Theatres’, to help employees shape the design, ‘see the future’, and become advocates of the solution back in their part of the business.
5.
overhead
The cost of delivering de-scoped capability at a later date is likely to be higher than the cost of delivering through existing GDFO programme given set up costs and overheads.
register
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
contract
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
load
Other improvements include:
a) automation and reduction of labour intensive and inconsistently operated manual processes; b) a step change in the ease of field data capture through improved scripting and workflow on mobile devices; c) Improved data quality through system driven data cleanse prior to load into new systems suite.
guide
The systems design and process refresh have been guided by Gas Distribution’s customer strategy and its 5 guiding principles.
recently
To get best value from the investment and leverage additional value Gas Distribution has recently redesigned its operating model.
connection
Release 2 and 3 core scope within the existing budget includes:
a) Release 2 - Full emergency roll out, contact centre telephony refresh and SAP Customer Relationship Management system delivery to contact centre. b) Release 3 – Replacement of TEAR, Storms (work management system for Constuction and Repair activities), AQS and QS (Quotation systems for connections activities).
description
Option 1: Reduce scope and continue with existing budget
a) Description – Reduce the scope of Release 2 and 3 to ensure no cost overrun.
modify
This investment will mitigate the risk of system failure and address the increased cost of maintaining and modifying systems currently running beyond the end of their supportable life.
continuous
Improved management information will support continuous process improvements helping the business achieve leading cost efficiency, customer satisfaction and safety performance.
14.
each
Each deployment takes between 4 and 5 months to implement.
strong
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
increasingly
In particular the objective to “become more efficient through transforming our operating model and increasingly aligning our processes.”
4.2
communicate
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls t...
bang
Release 2 and 3 will have a phased deployment that mitigates the risk associated to big bang implementation events.
removal
Actions include:
a) Strong commercial controls with key suppliers, including productivity improvements, reduced unit prices, fixed price contracts, fees at risk, removal of hourly charging. b) Reduced scope of mobile device replacement. c) Re-using design components and reduction in solution customisation. d) Increased off-shoring of design, build and test activities to Wipro India to benefit from labour arbitrage compared to other IT suppliers. e) Effective and early prioritisa...
as such
As such planned benefits may be at risk because it may not be possible to implement all planned business changes due to constraints on performance.
procure
Integrated end state design is complete covering all processes and systems, key vendors have been engaged, licences for all major systems have been procured and programme methodology developed with supporting tools in place.
in this
The implementation plan for the new Operating model will be integrated with the deployment of Gas Distribution Front Office programme with the objective of ensuring the new organisation achieves the savings described in this paper.
8.6
product
This will eliminate manual processing associated with time sheeting and product ordering, data will be loaded directly into our core systems through the handheld device reducing errors allowing our field engineers to focus on job execution and customer service.
e) A best of breed geospatial information system (ESRI) to display a single accurate geographic view of asset and work information to the business in the field, operational support and customer services.
equipped
Sustainable execution risk
There is a risk that it is not possible to execute the required business changes to deliver Opex savings in a sustainable manner because the organisation is not equipped to deliver the level of change envisaged in the business case.
electricity
The current Electricity Distribution price control review includes proposals for a customer service incentive that is likely to follow into the next Gas Distribution price control.
successful
Additionally, it is widely recognised that the successful transformation of systems and processes is critically dependant on the level of acceptance by those impacted by it.
services
These include:
a) Contact Centre Strategy – Contact Centre rationalisation project, value circa £2m/year operating efficiencies and circa £6M/year property rationalisation. b) Customer Services Incentive – estimated +/- £12m. 8.
alongside
Gas Distribution is committed to customer service excellence, prioritising it alongside safety and financial performance.
step
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
architecture
The diagrams below summarises the to be applications architecture:
Appendix B – Like for like replacement option 16.
next
Writing off design costs
There is a risk that any reduction in the scope of Release 2 and 3 will necessitate the writing down of design costs for functionality that does not form part of the next two Releases.
intelligence
Systems will support close coupling of complaint and feedback information with intelligence drawn from MI to help drive process improvements.
section
Given the budgetary constraints documented in section 3 there are two clear options for completing Release 2 and 3 of the programme.
5.3
period
The deployment window is limited to a 7-month period from April and October to avoid peak Emergency and Repair workload during the winter.
needs
This change will drive an increased focus on the efficient delivery of end to end processes, in order to better meet the needs and demands of customers and stakeholders.
4.3
therefore
Therefore the following functionality would not be delivered:
Mobile geographical information system for the field force, this will result in the continued use of CD maps.
fund
Mitigations:
Submission of a Board Paper requesting additional funding to complete the programme based on Option 2. 8.5
adjust
The requirement to replace these systems was identified at the time of the last price control, and £65m Capex and £14m Opex (adjusted for inflation) was included in National Grid’s submission.
there
Given the budgetary constraints documented in section 3 there are two clear options for completing Release 2 and 3 of the programme.
5.3
central
Marked reduction in customer handoffs and increased first call resolution as a result of improved and timely access to information (central customer database, asset register, GIS).
b) To be kept informed – Automated process steps that ensure customers are informed on progress and changes to work.
directly
This analysis has only incorporated benefits directly attributable to the introduction of the new front office systems.
all
As such planned benefits may be at risk because it may not be possible to implement all planned business changes due to constraints on performance.
wasted
The new scheduling and dispatch capability and improved management information and reductions in wasted travel time are likely to have a positive impact on safety and environmental performance.
23.
guided
The systems design and process refresh have been guided by Gas Distribution’s customer strategy and its 5 guiding principles.
representative
These providers were selected through a procurement exercise involving selection boards chaired by David Lister and Peter Massey including representatives from across the business.
3.4
technical
The remaining expenditure covers completion of detailed design, systems build, testing, training and deployment of each release plus technical infrastructure costs.
2.6
boards
These providers were selected through a procurement exercise involving selection boards chaired by David Lister and Peter Massey including representatives from across the business.
3.4
involve
These providers were selected through a procurement exercise involving selection boards chaired by David Lister and Peter Massey including representatives from across the business.
3.4
subject
The National Grid Group Executive is invited to:
a) APPROVE the increase in the total investment to £179m Capex, £26m Opex, and £46m of severance costs required to complete the programme. b) NOTE that subject to approval by National Grid Group Executive this paper will be submitted for final approval at the National Grid Board meeting on 15th December 2010. c) DELEGATE authority to the GDFO Steering Committee for the programme including changes to scope and expenditure that would ...
better
As a consequence of these changes, the IRR of the total programme will reduce from 16% to 15% but the incremental IRR of 22% still remains significantly better than the like for like replacement envisaged at the time of the Price Control submission of -1%.
1.5
engage
Integrated end state design is complete covering all processes and systems, key vendors have been engaged, licences for all major systems have been procured and programme methodology developed with supporting tools in place.
potential
The implementation of new front office systems is an enabler that offers the potential for a step reduction in Opex costs for National Grid.
being
This will be optimised through the use of the Click resource management tool being implemented for Repair in Release 3, and delivers a £0.6m benefit.
d) The creation of a standard set of planning tools to optimise designs will not only improve their quality but also significantly reduce rework.
equip
Sustainable execution risk
There is a risk that it is not possible to execute the required business changes to deliver Opex savings in a sustainable manner because the organisation is not equipped to deliver the level of change envisaged in the business case.
slip
Overrun risk
There is a risk that Release 3 could slip 5 months into 2012 if there are any delays in either release 2 or 3 design build or test phases.
request
Mitigations:
Submission of a Board Paper requesting additional funding to complete the programme based on Option 2. 8.5
sustained
The requirement to replace front office IT systems has created the opportunity for Gas Distribution in the UK to progress the Common Operating Model by automating business processes to deliver a sustained improvement in performance.
requested
Approval is now requested to invest the remaining £112m of Capex, £24m of Opex and £43m of severance costs to complete the programme.
regime
This is particularly important for Gas Distribution as it prepares for the incentive/penalty regime associated to customer satisfaction performance that is likely to be introduced as part of the next price control.
6.
gap
An integrated and sustainable risk control framework will be implemented that:
a) links agreed control objectives to the key controls embedded in business process designs, reducing the risk of control gaps and excessive controls; b) where possible, will drive efficiency and effectiveness through intelligent control design and use of systems based controls; c) can be communicated to interested stakeholders, for example assurance providers, and enable the impact of any new controls t...
inflation
The requirement to replace these systems was identified at the time of the last price control, and £65m Capex and £14m Opex (adjusted for inflation) was included in National Grid’s submission.
not
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
particularly
This is particularly important for Gas Distribution as it prepares for the incentive/penalty regime associated to customer satisfaction performance that is likely to be introduced as part of the next price control.
6.
retained
The benefits associated with the introduction of this system will be retained until it is replaced in 2020/21.
June
The scope of the IT systems to be replaced and enhanced through the Gas Distribution Front Office programme is described in Appendix A. This scope was signed off by the Programme Steering Group on the 9th June 2009.
3.2
force
Through Release 1 the programme has successfully built, tested and deployed a range of capabilities to the business including a smart travel, GPS solution to field force vehicles.
remainder
This has lead to a 12% increase in custom components which has resulted in 11% increase in the cost of R2 and R3.
d) Change in resource mix, the increased level of third party resources was required to address the non-availability of NG staff with specialist skills and capabilities compared with the assumptions used at the time of the November Board paper; resulting in an increase of £8m. e) Contingency, this is required to manage the complexity and uncertainty associated with the delive...
number
The Capex costs increases since the November 09 Board paper are driven by a number of factors:
a) New scope, this covers functionality that was not in scope at the time of the November 2009 Board paper but has subsequently been demonstrated to be essential to support delivery of the business case, compliance and customer strategies; resulting in an increase of £5M. e.g.
introduce
This is particularly important for Gas Distribution as it prepares for the incentive/penalty regime associated to customer satisfaction performance that is likely to be introduced as part of the next price control.
6.
calculated
Costs to Achieve
a) Costs to achieve are predominantly severance and have been calculated based on analysis of the workforce’s age profile, and agency and contractor levels at a company level.
confidence
In addition a number of adjustments have been made which have increased confidence in the delivery of the value enabled by the programme.
March
The Gas Distribution Front Office programme is currently scheduled to run from March 2009 until January 2012.
seek
The programme will seek to deliver a systems and process transformation that delights customers, makes life simpler for our people, makes us more productive and enhances our process and data controls.
1.2
arise
Specific process and control issues arising from the Project Nelson investigation are actively being used to inform the design.
4.4
expensive
Where possible standard “out of the box” functionality continues to be the preferred solution, which minimises the risk of expensive customisation.
avoid
The deployment window is limited to a 7-month period from April and October to avoid peak Emergency and Repair workload during the winter.
apply
To ensure the programme delivers the expected transformation three key criterion are being applied to all elements of the process and system solution:
a) Will it delight our customers? b) Will it make life simpler for our people? c) Will it make us more productive? 4.3
selection
These providers were selected through a procurement exercise involving selection boards chaired by David Lister and Peter Massey including representatives from across the business.
3.4
penalty
This is particularly important for Gas Distribution as it prepares for the incentive/penalty regime associated to customer satisfaction performance that is likely to be introduced as part of the next price control.
6.
compromise
There is a risk that poor employee engagement and trade union relationships will compromise the delivery of the required business changes adversely impacting the forecast savings.
given
Given the budgetary constraints documented in section 3 there are two clear options for completing Release 2 and 3 of the programme.
5.3
Post
Business Case Model Assumptions
a) RAV effective asset life = 45 years b) Financial depreciation on 20% reducing balance c) Pre-tax PCR return = 5.99% d) Post-tax PCR return = 4.94% e) IQI factor = 36%
taken
A delay of between 5 and 6 months is likely to cost £15m to £20m even after actions to mitigate costs have been taken.
Peter
Appendix D: November 2009 Board Paper
National Grid Board Gas Distribution Front Office Programme A paper by Peter Massey for Mark Fairbairn, Executive Director, Gas Distribution 1. |
Word List Actions:Create a new Word List |
